Belgian Council of State pierces the veil of a PPP project
11/11/2009

In the Horizon Pleiades case, the Council of State was confronted with an interesting question: if a public authority organises a procedure to select its partner for a PPP company, which will perform works or services which would normally be covered by the Procurement Directives, does the selection procedure have to comply with the rules laid down in the Procurement Directives or can a “light” selection procedure be used? In its ruling, dated 19 June 2009, the Council of State pierced the veil of a so-called“partnership tender procedure” and held that it must comply with the rules laid down in the Directives.
 
Idelux, an inter-municipal company, wished to set up a PPP company to prepare, study, build and sell the first rural ‘eco-district’ in the Belgian Province of Luxemburg, at Bellefontaine, near Tintigny. Idelux organised a “light” procedure to select its private-sector partner for this PPP company. The notices in the Belgian official gazette and in the Official Journal indeed indicated that this was not a “procurement procedure”, but rather “a request for partnership”.
 
According to the notice, there were several selection criteria, but only one concerned the PPP company, whereas the others related to the works and services to be carried out.
 
There were three candidate partners: Horizon Pleiades, Thomas & Piron and Tpalm. Idelux allowed Thomas & Piron to proceed to the second round of selection, but not Horizon Pleiades, even though the latter had the highest score for the (one) criterion relating to the proposed creation of the PPP company.
 
Horizon Pleiades appealed against this decision by Idelux to the Council of State, asking it to suspend and annul Idelux’s decision, arguing that Idelux had acted illegally by not allowing Horizon Pleiades to go forward to the second round. 
 
Horizon Pleiades argued that what Idelux called a “partnership” was either a public service contract, or a ‘disguised’ public development contract, and that therefore Idelux should have applied a procurement procedure compliant with the Procurement Directives instead of the  “light” version it had used.
 
Horizon Pleiades argued that Idelux:
-       had illegally used the negotiated procedure;
-       had not determined adequate and relevant qualitative selection criteria;
-       had not split the qualitative selection phase from the negotiation phase of the bids; and
-       had not predetermined the award criteria.
 
In its judgment of 19 June 2009, the Council of State suspended the decision by Idelux, thus demonstrating an interesting approach to the creation of “legal vehicles” as a means of avoiding the application of public procurement rules.
 
Even though the Council of State stressed that the procedure for selecting private-sector partners for public authorities in PPP companies does not fall within the scope of the Belgian and European procurement rules, it also held that the public procurement rules did apply to selection procedures for partnerships which were mere ”constructions” to get around the application of the public procurement rules.
 
In this respect, the Council of State referred to the EC Interpretative Communication of 5 February 2008 on the application of Community law on Public Procurement and Concessions to Institutionalised Public-Private Partnerships (“IPPP”) (n° C(2007) 6661) and particularly to the following paragraph: “If the task assigned to the public-private entity is a public contract fully covered by the Public Procurement Directives, the procedure for selecting the private partner is determined by these Directives.”.
 
The Council of State then examined whether or not there were sufficient arguments to pierce the veil of this “construction” and to qualify it as “procurement”. The Council of State saw two main arguments.
 
First, it found that the qualitative selection by Idelux was mostly based on criteria regarding the services to be provided, and less on criteria relating to the partnership, and that this was the case both in the tender documents and in the evaluation report. This was the main reason why Horizon Pleiades’ bid was unsuccessful, even though it was ranked first using the criteria for the creation of the PPP company.
 
Second, the Council of State considered that it appeared that the works to be carried out would in fact “correspond to the requirements specified by the contracting authority” (here: Idelux) in the sense of Article 5 of the Belgian Procurement Act. This is an element that comes from the definition of “public works contract” (See: Art. 1(2)(b) of Directive 2004/18).
 
Based on those two important arguments, the Council of State “pierced” the veil of the partnership construction and was of the opinion that Idelux should have organised a proper procurement procedure.
 
Public authorities are hereby warned: the mere qualification as a “partnership” is not sufficient to disregard the proper procurement rules. The Belgian Council of State will effectively verify whether or not a “partnership construction” is in fact a “hidden” procurement for works, services or supplies or a “hidden” concession.

Related : ALTIUS ( Mr. William Timmermans )

[+ http://www.altius.com/en/knowledge-base/recent-publications/2009/11/11/belgian-council-of-state-pierces-the-veil-of-a-ppp-project/]


Click here to see the ad(s)
All articles Private Public Partnership

Lastest articles Private Public Partnership

De spontane aangifte van self-cleaning measures om uitsluiting te vermijden : het Hof van Justiti...
01/03/2021

Naar aanleiding van een Belgische zaak, is het Hof van Justitie recent ingegaan op de vraag naar de mogelijkheid van een k...

Read more

COVID-19 and public procurement in Belgium
01/04/2020

Measures have been taken by the Belgian authorities to respond to the COVID-19 pandemic. These measures have serious reper...

Read more

Flemish Decree on Major Projects and Programmes
06/05/2019

On 27 April 2019, a Flemish decree establishing a framework for major projects and programmes entered into force. The decr...

Read more

New provisions regarding exclusion grounds in public procurement: corrective measure
04/05/2017

The new public procurement legislation, which is expected to enter into force on 30 June 2017, contains new provisions for...

New provisions regarding exclusion grounds in public procurement: corrective measure Read more

Lastest articles by Mr. William Timmermans

Nitrogen crisis in Flanders? A recent judgment may have serious consequences
09/03/2021

On 25 February 2021, the Flemish Council for Permit Disputes annulled a permit for the construction and operation of two l...

Read more

CJEU rules that national sports governing bodies can be subject to public procurement law
05/02/2021

On 3 February 2021, the Court of Justice of the European Union (“CJEU”) issued an interesting ruling in a case...

Read more

ECJ holds that a single award procedure is sufficient for IPPPs
12/11/2009

The Acoset judgment of  the ECJ dated 15 October 2009 (C-196/08) was related to a dispute about an institutionalised ...

ECJ holds that a single award procedure is sufficient for IPPPs Read more

LexGO Network